Agenda Item (VI-B-5-b)

Meeting10/16/2012 - Regular
Agenda ItemConsent Agenda Action (VI-B-5-b)
SubjectBid Awards for the ADA Transition Plan Implementation Project - Phase 1 Barrier Removal for Moreno Valley and Norco Colleges – Trade Categories 1-6
College/DistrictDistrict
Funding
Measure C
Recommended ActionIt is recommended that the Board of Trustees award the ADA Transition Plan Implementation Project - Phase 1 Barrier Removal for Moreno Valley and Norco Colleges – Trade Categories 1-6, for the total bid amount of $1,277,000 to the contractors listed on the attached and authorize the Vice Chancellor, Administration and Finance to sign the associated agreements.

Background Narrative:


On September 25, 2012, the District received bids in response to an Invitation for Bid solicitation for the ADA Transition Plan Implementation Project - Phase 1 Barrier Removal for Moreno Valley and Norco Colleges. See the attached Lowest Responsive and Responsible Bidder list summary and the related detailed list of Bid results.

 

 

References for all listed contractors were checked by District staff and found to be satisfactory.

 

 
Prepared By: Jim Buysse, Consultant, RCC
 Calvin Belcher, Project Manager
Majd Askar, Director of Business Services

Attachments: